Home

Posted on: July 31, 2017

2017 Pavement Rehabilitation Program - Project Update as of October 4, 2017

Sundown Terrace

Raising of existing utilities back to top of newly paved roadways will continue through October. On the newly paved roadway, replacement roadway striping installation has begun for locations on the south side of Highway 24, the remaining streets will be striped in early November.

Pulverizing, roadway grading and cement treating work was completed last week on:

  • Sundown Terrace
  • Redcoach Lane
  • Candle Terrace
  • Upper & Lower Van Ripper Lane
  • Sunnyside Court

New HMA paving completes this week at the follow locations:

  • Sundown Terrace
  • Redcoach Lane
  • Candle Terrace
  • Upper & Lower Van Ripper Lane
  • Sunnyside Court
  • El Nido Ranch Road

El Nido Ranch Road roadway repair will consist of milling the existing to 3-inches and repaving, with a possibility of additional, deeper repairs to isolated locations. This work will take place during this week.

Storm drain pipe replacement work is now complete on the project, but there will be miscellaneous follow up work to fix or improve minor issues throughout the project in October. Concrete replacement work is complete for most of the project, there will likely be minor repairs and/or additions needed at various locations throughout the project. Utility location potholing & relocation work is now complete.

New Asphalt curb & gutter layout work is ongoing, installation is scheduled for mid-October; all locations, north & south of Highway 24, will be installed within a one-week time frame.

Follow-up completion efforts, corrective work & damage repair work throughout the project will be started next week and run through the month of October. The projected date for project completion is November 17, 2017.

Read More
Facebook Twitter Google Plus Email

Other News in Home

Streetfeast3

Food Truck Thursdays!

Posted on: August 8, 2017
STR_pic

Short Term Rentals

Posted on: August 24, 2017